Facilities
Campus Updates
8.20.25 - No new updates
Art and Music Portable
Front Building
- 01.13.25 - All remaining cabinets and countertops have been installed.
Kinder and Fourth Grade Portables
-
05.05.25 - Remediation is complete on fourth grade portables, and we received clearance for build back.
-
05.02.25 - Aristoi is working with our portable vendor for build back. Target start date is 5/12/2025.
Bathrooms
Miscellaneous
- 07.10.25 - Floors are scheduled to be deep cleaned and waxed next week. HEPA filters for each HVAC unit are being replaced. Skirting for classrooms M1-M6 will be installed within the next week.
Campus Testing
HVAC Units
B Building
C Building
- 08.05.25 - C building is open for classes.
- 07.11.25 - The rebuild of the C building is underway. The roof insulation and exterior wall insulation has been installed. Ceiling tiles in the building are being installed followed by the vinyl coated walls. As rooms are completed with the walls, the flooring will be installed. The vendor anticipates a completion date of 8/5/2025 assuming no issues.
D Building
- 07.11.25 - Releveling of the building is complete. Roof repairs are scheduled for next week. Floor repairs are scheduled for July 21.
- 03.14.25 - D20 (Receptionist) was tested. No elevated levels of mold were found. After remediation was completed in D22 (Student Care), the area was retested and cleared to reopen on March 14, 2025.
E Building
- 07.11.25 - Releveling of the building is complete. Roof repairs are scheduled for next week. Floor repairs are scheduled for July 21.
G Building
- 05.05.25 - G2 has been fully restored and students resumed classes 04.30.25.
- 04.22.25 - Build Back in G2 will begin today.
- 04.17.25 - Remediation in G2 is complete. It was retested and cleared for the rebuild process to begin as of April 17, 2025.
- 04.12.25 - The remediation vendor will be on campus to begin working in G2. Once the classroom has been remediated and cleared, the rebuilding of the classroom will begin.
- 03.27.25 - Additional testing was conducted in G2 and the room tested positive for elevated levels of mold. A licensed remediator is being contacted to remediate the classroom.
H Building
- 03.27.25 - No elevated levels of mold were identified as being present in the air samples collected in H1 or H2.
Miscellaneous
- 06.13.25 - Update
This site provides information using PDF, visit this link to download the Adobe Acrobat Reader DC software.